Advertisement
News

Environmentalist's challenge over Co Cavan weather mast planning permission dismissed

May 6, 2022 11:40 By News Northern Sound
Environmentalist's challenge over Co Cavan weather mast planning permission dismissed
Share this article

Val Martin had challenged the board's decision in October 2020 to grant permissions to Raragh Developments for a meteorological mast.

An Environmentalist has lost his High Court challenge against An Bord Pleanála's decision to grant permission for a weather mast at a wind farm in Co Cavan.

Val Martin had challenged the board's decision in October 2020 to grant permissions to Raragh Developments for a meteorological mast and the retention of associated developments at the five-turbine Raragh Wind Farm, Corrinshigo, Co Cavan.

Mr Martin, a farmer and environmental campaigner who lives near the wind farm, is also the Irish spokesperson for the "European Platform Against Wind Farms."

Advertisement

The wind farm was built in 2019 and became operational in 2020.

Planning permission for the wind farm, which included an 85m weather mast at a specified location on the site, was granted in 2010.

The mast was not completed alongside the turbines.

Advertisement

In 2020, Cavan County Council granted permission for the completion of the weather mast at a different location on the site, which Mr Martin appealed to the board.

The board, whose inspector recommended that permission be granted, upheld the Council's decision to give the mast the go ahead.

Mr Martin brought judicial review proceedings against the board, aimed at having its decision set aside.

Advertisement

Mr Martin argued that the planning authority's decision was flawed because permission for he proposed mast was granted in the absence of an Environmental Impact Assessment, in circumstances where the mast was being relocated from its original site, being carried out.

An EIA report on the proposed mast should have been, but was not, carried out in respect of the mast, it was claimed.

The application proceeded before the High Court by way of a telescoped hearing, where the judge considered both the application for leave to bring the action, and the full action itself.

Advertisement

In his judgement, Mr Justice Cian Ferriter rejected Mr Martin's arguments and refused his application for permission to apply for judicial review.

The court did not accept that substantial grounds had been made out that would allow the court to grant leave to bring the action.

The judge also held that neither the board, nor its inspector, had erred by finding that an EIA was not required.

Advertisement

The judge said the mast was part of the original wind farm project, which was the subject of planning permission and EIA.

The mast did not constitute a further or separate stage of the project, he said.

The change of the location of the mast, the judge added, did not render that development as being a new project and did not give rise to any likely significant effect on the environment, the judge added.

Share this article
Advertisement
Advertisement

NorthernSound Newsletter

Sign up now to keep up to date with the latest news.

Processing your request...

You are subscribed now! please check your email to confirm your subscription.

Copyright © 2024 Northern Sound FM. Developed by Square1 and Powered by PublisherPlus